Beginning Monday, August 24, street resurfacing will begin on the following streets:

Persons Court between Lake Avenue and Woodland Avenue
Oakwood Drive between Penfield Avenue and Clemens Avenue
Bell Court between Clemens Ave and house 1250
No parking will be permitted in these work zones weekdays from 7:00am until 7:00pm or while crews are present.
The roadways will first be milled and then repaved. Milling is anticipated to be completed by the evening of Monday, August 24, paving will follow at a later date.
Access to driveways will be maintained throughout the project.
Traffic will be maintained; however, delays should be expected.
Please plan accordingly, use alternate routes when possible, and use extra caution while traveling through the work zone. We appreciate your patience and cooperation while this
improvement project is completed.