Effective Monday, October 9th, 2023:
The Poplar & Gulf Rd. project is progressing!
Construction on Gulf Rd., at Dilworth will begin on Monday, Oct. 9, 2023. The construction will continue south (towards downtown Elyria). There will be increased construction activities, i.e.: workers, vehicles, barrels, etc. Please continue to use caution, and SLOW down.
Later next week (week of Oct. 9), the Brandtson and Poplar St. intersection will be closed. This will enable the placement of the diversion chamber for the sewer project.
Poplar between Olive and Longfellow is anticipated to be completed next week.
This is all weather dependent!
Again, thank you for your continued patience!